New round of paving work to begin in June

by

Image courtesy of surasakiStock at FreeDigitalPhotos.net

The city of Homewood has its paving priority list set for this fiscal year and will begin work in June.

Public Services Director Berkley Squires said the paving list was determined with the help of Volkert Engineering, which was contracted in 2016 to grade all roads in the city and create a priority list for repairs based on the condition. The city has followed that list in paving since 2016, though work by utility companies has changed some of the priorities over time.

Squires said the utility companies had to be consulted before creating the 2019 list to avoid freshly paving a road and having it cut open shortly after to access a power, water or gas line.

The paving priorities for this year are:

Squires said work is expected to last through the summer until September. The city budgeted $1 million for paving this fiscal year, which he said should cover all of the above projects.